The National Grid Corp of the Philippines (NGCP) has proposed the upgrade of Cebu’s transmission lines to meet the island-province’s growing demand and to accommodate future power projects. In a regulatory filing, NGCP sought the Energy Regulatory Commission’s approval of the P424.4 million Cebu-Lapu-Lapu Transmission Project, which involves the installation of an additional 138 kiloVolt (kV) circuit from the Cebu substation to the Lapu-Lapu substation using overhead and submarine transmission lines.

The proposed transmission lines will run parallel to the existing Cebu-Mandaue-Lapu-Lapu 138 kV line. This facility delivers bulk of the power requirements of Cebu.  NGCP said the Cebu-Mandaue-Lapu-Lapu 138 kV line needs to be supported on account of the growing demand in the province, as well as the addition of new generating plants with a total cumulative capacity of 794 megawatts through 2019.

“By the year 2015, the Cebu-Mandaue 138 kV line could be overloaded by more than 33 percent of its rated transmission capacity during N-1 condition, which will result in a power curtailment of about 68 megawatts,” NGCP said.

N-1 refers to the grid’s ability to operate even with the loss of a major component such as a tripped power plant or transmission line.

“Similarly, the Mandaue-Lapu-Lapu 138 kV line could exceed its rated capacity by 59 percent during a single circuit outage, which will result to a power curtailment of approximately 57 megawatts,” NGCP said.

“Considering the necessity to construct the project in order to maintain the normal operating levels of the Cebu-Mandaue and the Mandaue-Lapu-Lapu 138 kV transmission lines and to avoid power curtailment, the implementation of the project must commence as scheduled. As such, pre-construction activities are needed to be undertaken in 2013 in order to meet the target completion in 2015,” the company said.

Chaired by a son of mall tycoon Henry Sy, NGCP is a privately owned corporation in charge of operating, maintaining, and developing the country’s power grid. It transmits high-voltage electricity through “power superhighways” that include the interconnected system of transmission lines and towers, substations and related assets. Apart from the Sys, other shareholders of NGCP are the Coyuitos and State Grid Corp of China.

Pimagazine Asia Admin

Recent Posts

Insuring Wind Turbines, What is the Risk?

Gallagher Re has shed light on the significant challenges insurers face when providing coverage for…

8 months ago

ARENA Start Feasibility Study in Western Australia

The Australian government will disburse AUD 1.7 million (USD 1.1m/EUR 1m) in grant funding to…

8 months ago

Asia moving away from Solar?

GlobalData’s latest report, ‘Asia Pacific Renewable Energy Policy Handbook 2024’ is among the latest region-specific…

8 months ago

Asia’s Energy Challenge 2024

The electrical generation market is facing a number of challenges, including the need to increase…

8 months ago

Powering Progress: Nuclear Energy’s Role in Asia’s Energy Landscape

Nuclear energy has emerged as a prominent player in Asia's energy landscape, offering a reliable…

1 year ago

Charting a Cleaner Path: Carbon Capture and Storage in Asia

The pursuit of a low-carbon future has gained significant momentum globally, and Asia stands tall…

1 year ago